What is required when sub-metering end-uses for EA Credit Advanced Energy Metering?

  1. Manual data entry

  2. Use of standard meters

  3. Use a building automation system (BAS) or software for data collection

  4. Periodic meter readings

The correct answer is: Use a building automation system (BAS) or software for data collection

When pursuing EA Credit Advanced Energy Metering, utilizing a building automation system (BAS) or software for data collection is essential. This is because advanced energy metering aims to provide real-time monitoring and data management of energy consumption within a facility. A BAS or compatible software allows for automated data collection and analysis, which enhances the efficiency of tracking the energy performance of various end uses within the building. By using a BAS or software, building operators can gain insights into energy consumption patterns, identify inefficiencies, and facilitate better decision-making regarding energy management. This method supports continuous improvement and aligns with the objectives of LEED by promoting sustainability and energy efficiency. In contrast, methods like manual data entry or periodic meter readings do not provide the same level of immediacy and ongoing data management that a BAS or software solution offer. Standard meters alone may not enable the sophisticated data analytics that are critical for maximizing energy efficiency and achieving LEED certification objectives.