LEED AP with Operations and Maintenance (O+M ) Practice Exam

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the LEED AP with O+M Test. Utilize flashcards and multiple-choice questions with detailed hints and explanations. Excel in your upcoming examination!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


How many total meters are needed for a campus project with 5 buildings, each receiving potable water from public supply, to comply with WE Prerequisite Building Water Metering?

  1. 3

  2. 4

  3. 5

  4. 6

The correct answer is: 5

To ensure compliance with the Water Efficiency (WE) Prerequisite for Building Water Metering, each building in the campus project must have an individual water meter. Since there are 5 buildings on the campus, this translates to needing a separate meter for each building to facilitate accurate tracking and management of water consumption. The prerequisite emphasizes the importance of measuring and monitoring water usage to promote efficient water management practices, identify trends in consumption, and support efforts to reduce overall water usage. Therefore, in this context, installing one meter per building leads to a total of five meters needed for the entire campus. Thus, the correct total number of meters required for compliance is indeed five, corresponding to the number of buildings in the project.