A project has created a corrective action plan for EQ Credit: Occupant Comfort Survey. What must it include?

  1. Changes to the building structure

  2. Long-term financial investments

  3. No-cost measures like adjustments to equipment run-time or changes to procedures

  4. Expensive renovations to the project

The correct answer is: No-cost measures like adjustments to equipment run-time or changes to procedures

The correct answer involves no-cost measures like adjustments to equipment run-time or changes to procedures. When addressing occupant comfort in a building, the focus is often on practical solutions that can be implemented quickly and at minimal expense. Corrective action plans are intended to respond to issues identified in the occupant comfort survey effectively while also being feasible for the facility management team to execute. Implementing no-cost measures typically involves making small adjustments that can significantly improve the comfort level of occupants without requiring substantial financial investment or extensive renovations. For instance, changing the run times of HVAC systems or modifying operational procedures can help address issues like temperature fluctuations or air quality problems that occupants experience. Other options, such as changes to the building structure or expensive renovations, may be required in some cases to enhance occupant comfort, but they do not necessarily constitute immediate corrective actions. Instead, they often involve a longer-term investment of financial and time resources and may be outside the scope of a quick corrective action plan. Additionally, long-term financial investments would not fall under the immediate corrective measures expected from the EQ Credit related to occupant surveys, emphasizing the value of accessible and quickly actionable solutions.